Update 5 - 8.15.26

Review:

  1. Lower level slab was poured from GG-K.

  2. Masonry walls at lower level are ongoing. The elevator shaft was topped out and plan N wall is ongoing. 

  3. Foundations at the lobby level were completed.

  4. Masonry walls to grade at the upper level Sanctuary perimeter are ongoing.

  5. Plumbing rough ins were complete at the lobby level.

  6. Lobby Level slab prep has begun.

  7. Electrical rough ins will continue with slab prep.

  8. Waterproofing and foundation drain is ongoing around the building perimeter.

  9. Haul off of spoils is ongoing.