10.3.26
Steel detailing will be finished on Monday, 10/5. The steel inspector has inspected 90%.
Wood Framing is ongoing in the lobby area. Walls and trusses installed.
Concrete diamond pours, grouting of base plates, and slab on deck at mezzanine level are scheduled for next week.
10.19.26
Wood framing at exterior walls is ongoing.
Sanctuary stage wood framing is ongoing.
Wood framing at sanctuary high roof is ongoing.
Concrete slab on deck at mezzanine level is complete.
Existing main electrical panel has been demolished and installation of new electrical equipment will be completed today.
10.26.26
Wood framing at exterior walls is ongoing.
Wood floor framing is ongoing.
Wood framing at sanctuary high roof is ongoing.
Intumescent paint primer has been installed
Steel Stairs have been installed.
Masonry angle at plan West wall has been installed.
10.31.26
Wood framing at exterior walls is ongoing.
Wood framing of interior walls is ongoing
Wood floor framing is ongoing.
Wood framing at sanctuary high roof is ongoing.
Intumescent paint has been completed.
Grading and installation of storm structures and piping plan west of D-Line is ongoing.
Cold-formed metal framing at the exterior sanctuary perimeter has commenced and is ongoing.

