Update 7 - October
10.3.26
Steel detailing will be finished on Monday, 10/5. The steel inspector has inspected 90%.
Wood Framing is ongoing in the lobby area. Walls and trusses installed.
Concrete diamond pours, grouting of base plates, and slab on deck at mezzanine level are scheduled for next week.